East–West Corridor Upgrading, Section 4

Widening and reconstruction of a 21 km highway section carrying continuous freight traffic, including cross-drainage replacement and a reconstructed urban section through two market towns.

Project data

Client
[Sample] Department of Roads
Location
Morang, Koshi Province
Sector
Transportation
Contract type
Item-rate contract with performance-based maintenance period
Duration
28 months (in progress)
Completion
Ongoing · 2026
Contract value
[Sample] NPR 1.8 billion

Scope of work

  • 21 km of carriageway widening from 7 m to 11 m
  • Full-depth pavement reconstruction on 9 km of failed sections
  • 34 cross-drainage structures replaced or extended
  • Two urban sections with kerbs, footpaths and covered drains
  • Road furniture, marking and safety barrier installation
The challenge

What made this difficult.

  • 01

    The corridor carries continuous freight; full closure was not permitted at any point.

  • 02

    Two market towns along the alignment have shopfronts directly abutting the carriageway.

  • 03

    The original drainage was undersized, causing recurring pavement failure at 34 locations.

The engineering solution

What we did about it.

  • 01

    Construction is staged in 800 m sections with half-width working and signed diversions, maintaining one lane in each direction at all times.

  • 02

    Urban sections are built in short lengths with steel plate bridging to preserve shopfront access during working hours.

  • 03

    Cross-drainage capacity was recalculated against updated rainfall data, and structures upsized before pavement reconstruction.

  • 04

    Night working was introduced for asphalt laying in the urban sections, agreed with the municipality and notified to residents.

Key outcomes

  • Corridor length

    21 km

  • Drainage structures

    34

    Replaced or upsized

  • Traffic

    Maintained

    No full closure at any stage

  • Status

    Ongoing

Safety performance

  • Certified traffic management plan reviewed at every stage change
  • Trained flaggers and speed control on all live-traffic interfaces
  • Pedestrian routes maintained continuously through both urban sections
  • Plant proximity exclusion zones enforced with banksman coverage

Sustainability measures

  • Milled asphalt reclaimed and reused in shoulder and access construction
  • Dust suppression on all haul routes through settled areas
  • Drainage upgraded to reduce recurring failure and future reconstruction demand
  • Roadside tree replanting programme agreed with the local authority
Project gallery

During construction.

Pavement layer compaction with vibratory roller during reconstruction
Pavement layer compaction with vibratory roller during reconstruction
Box culvert replacement under a live carriageway
Box culvert replacement under a live carriageway
Urban section with new kerbs, covered drain and footpath
Urban section with new kerbs, covered drain and footpath
Field density testing on a completed base course layer
Field density testing on a completed base course layer