Rehabilitated hill road with new retaining structures and drainage on a steep slope
CompletedTransportation2022Sample record

Hill Road Slope Rehabilitation

Reinstatement of 3.2 km of hill road after monsoon slope failure, combining emergency access restoration with permanent stabilisation and drainage.

Project data

Client
[Sample] Road Maintenance Authority
Location
Sindhupalchok, Bagmati Province
Sector
Transportation
Contract type
Emergency response and rehabilitation contract
Duration
9 months
Completion
Completed · 2022
Contract value
[Sample] NPR 420 million

Scope of work

  • Emergency debris clearance and single-lane access restoration
  • Slope stabilisation across seven failure zones
  • Gabion, breast and reinforced soil retaining structures
  • Catch drains, cascades and cross-drainage reinstatement
  • Pavement reconstruction and bio-engineering works
The challenge

What made this difficult.

  • 01

    The road was the only access route for 14 settlements, and remained partially blocked at three points.

  • 02

    Further failure risk was active during the works, with continuing rainfall through the first two months.

  • 03

    Permanent solutions had to be designed while emergency clearance was already under way.

The engineering solution

What we did about it.

  • 01

    Emergency clearance restored controlled single-lane access within 11 days, ahead of permanent works design completion.

  • 02

    Failure mechanisms were assessed zone by zone; four zones required drainage correction rather than structural retention, reducing cost and construction time.

  • 03

    Slope monitoring with rain-triggered stop-work thresholds protected the workforce during the residual monsoon period.

  • 04

    Bio-engineering — vegetative planting on completed slopes — was used to sustain surface stability after handover.

Key outcomes

  • Access restored

    11 days

    Controlled single lane

  • Length rehabilitated

    3.2 km

  • Failure zones

    7

    All stabilised and drained

  • Settlements reconnected

    14

Safety performance

  • Rainfall-triggered evacuation protocol with defined thresholds and assembly points
  • Spotters posted above all active excavation faces
  • Controlled public access with escorted convoys during clearance
  • No slope-failure injuries recorded during the works

Sustainability measures

  • Bio-engineering planting on all completed slope faces
  • Local stone used for gabion and breast wall construction
  • Debris material screened and reused as fill where geotechnically suitable
  • Local labour and community groups engaged for planting and maintenance
Before & after

The change on the ground.

Road blocked by debris following monsoon slope failureBefore
Rehabilitated road section with retaining structures and drainageAfter

The corridor immediately after the failure, and after permanent stabilisation.

Project gallery

During construction.

Debris clearance operation restoring access after slope failure
Debris clearance operation restoring access after slope failure
Gabion retaining wall construction on a rehabilitated slope
Gabion retaining wall construction on a rehabilitated slope
Catch drain and cascade construction above the carriageway
Catch drain and cascade construction above the carriageway
Bio-engineering planting establishing on a completed slope face
Bio-engineering planting establishing on a completed slope face
Start a project

Have a project with similar constraints?

Send the brief. We will tell you what the delivery risks are before you commit to a programme.