Run-of-River Hydropower Civil Works
Headworks, waterway and powerhouse civil works for a run-of-river scheme, executed 47 km beyond the nearest sealed road with a fully self-sufficient site establishment.
Civil and structural works for a 132 kV substation, including equipment foundations, control building, cable trenching and site drainage, coordinated with the electrical installation contractor.
Equipment foundation setting-out tolerances were tighter than standard civil practice.
The electrical contractor's programme required foundations released in a non-sequential order.
The site had a high water table affecting cable basement construction.
Foundation setting-out was carried out with total station control and independently verified before every pour, with records issued to the electrical contractor at handover.
The construction sequence was re-planned around the electrical contractor's installation order rather than civil convenience.
The cable basement was constructed with a waterproof concrete design and external tanking, tested before backfill.
A joint weekly interface meeting kept foundation release dates and installation dates on a single tracked list.
Foundations
Released to sequence
Matched electrical programme
Setting-out
Verified
Independent check before each pour
Basement
Watertight
Tested before backfill
Handover
On programme
Headworks, waterway and powerhouse civil works for a run-of-river scheme, executed 47 km beyond the nearest sealed road with a fully self-sufficient site establishment.
A planned logistics park with warehousing, container handling yard and administrative facilities, currently at design coordination stage ahead of mobilisation.
A processing and cold-storage facility with heavy machine foundations and 14,000 m² of industrial flooring, phased so that equipment installation began five months before construction completion.
Send the brief. We will tell you what the delivery risks are before you commit to a programme.