Completed substation civil works with equipment foundations and control building
CompletedEnergy2021Sample record

132 kV Substation Civil Works

Civil and structural works for a 132 kV substation, including equipment foundations, control building, cable trenching and site drainage, coordinated with the electrical installation contractor.

Project data

Client
[Sample] National Transmission Utility
Location
Rupandehi, Lumbini Province
Sector
Energy
Contract type
Civil works package
Duration
13 months
Completion
Completed · 2021
Contract value
[Sample] NPR 360 million

Scope of work

  • Switchyard equipment foundations and structure bases
  • Control and relay building with cable basement
  • Cable trenches, ducts and earthing pit civil works
  • Site levelling, gravel surfacing, drainage and boundary wall
  • Fire wall and transformer bund construction
The challenge

What made this difficult.

  • 01

    Equipment foundation setting-out tolerances were tighter than standard civil practice.

  • 02

    The electrical contractor's programme required foundations released in a non-sequential order.

  • 03

    The site had a high water table affecting cable basement construction.

The engineering solution

What we did about it.

  • 01

    Foundation setting-out was carried out with total station control and independently verified before every pour, with records issued to the electrical contractor at handover.

  • 02

    The construction sequence was re-planned around the electrical contractor's installation order rather than civil convenience.

  • 03

    The cable basement was constructed with a waterproof concrete design and external tanking, tested before backfill.

  • 04

    A joint weekly interface meeting kept foundation release dates and installation dates on a single tracked list.

Key outcomes

  • Foundations

    Released to sequence

    Matched electrical programme

  • Setting-out

    Verified

    Independent check before each pour

  • Basement

    Watertight

    Tested before backfill

  • Handover

    On programme

Safety performance

  • Interface permits agreed with the electrical contractor for all shared work areas
  • Excavation support and edge protection on all trench and basement work
  • Lifting operations planned and supervised by an appointed person
  • Site induction shared across both contractors' workforces

Sustainability measures

  • Transformer bunds sized for full containment with oil–water separation
  • Site drainage designed to settle runoff before discharge
  • Excavated material reused in site levelling
  • Local labour engaged for boundary and civil finishing works
Project gallery

During construction.

Equipment foundation setting-out with survey instrument
Equipment foundation setting-out with survey instrument
Cable trench and duct installation across the switchyard
Cable trench and duct installation across the switchyard
Control building under construction
Control building under construction
Transformer bund and fire wall construction
Transformer bund and fire wall construction